# Assets and reserve study

> Record your depreciation report, seed a component registry from it, and turn the whole thing into a projection that tells you whether the reserve is enough.

Source: https://managestrata.ca/docs/property/assets-and-reserve-study

**Assets & reserve study** is where a depreciation report stops being a PDF and starts being a plan.

The page does three things: **records the study**, **holds the component registry**, and **produces the reserve projection**.

## Setting it up

The top of the page is three steps, each marked done once it is:

  1. **Upload the study**

   Upload the depreciation report under [Documents](https://managestrata.ca/docs/documents/library) and
   set its type to *Depreciation / reserve study*. Once it's there, the step
   links to it.
  1. **Record its details**

   **Record details** asks for the provider, the status, the **report date**
   (the date on the report, not today) and the next due date. This drives the
   depreciation deadline on
   [Compliance](https://managestrata.ca/docs/compliance/depreciation-report).
  1. **Build the component list**

   Extract it from the study, or add components by hand — below.

### Correcting the study on file

Once a study is recorded, the button reads **Update details**, and it **edits that study in place** — a wrong report date or a missing provider is corrected, not duplicated. A genuinely new report, five years on, is recorded from the depreciation report item on [Compliance](https://managestrata.ca/docs/compliance/depreciation-report#recording-the-report), which files it alongside the old one.

> **Get the report date right**
>
> Remaining lives in the registry are counted from it, and the next
> depreciation deadline is calculated from it. A date that's a year out moves
> both.

## The component registry

A **component** is a physical thing that will eventually need replacing, with a cost and a date. Roof, elevator, boiler, parkade membrane, windows, balcony railings, corridor carpet, intercom.

For each one you record:

| Field | Why |
| --- | --- |
| Name | What it is |
| Category | Groups it for filtering — see below |
| Replaced every (years) | How long it lasts when new |
| Remaining life (years) | How long until it needs doing — counted from the year the figure was written down |
| Replacement cost | Current dollars — update it as prices move |

A component needs **both a replacement cost and a remaining life** to count in the reserve projection. One missing either is still listed, marked *Not recorded*, and counted by nothing.

### Seeding from the report

With the study uploaded, **Extract from study** reads it and drafts the component list for you to review. Review what it added and remove anything that doesn't apply.

> **Seed it — don't type it**
>
> A registry built from memory will have five components in it and will produce a
> projection that looks wonderfully healthy. A registry seeded from the report has
> everything the professional found, including the things nobody on council knew
> about.

### Categories

Categories are offered from one list — **Site · Structural · Building envelope · Roofing · Interior finishes · Mechanical · Electrical · Plumbing · Elevating devices · Fire and life safety · Amenities · Other** — both to the extraction and as suggestions when you add or edit a component by hand, so the same thing lands in the same bucket however it got there.

They're suggestions, not a fixed choice. A category that isn't on the list — *Marina and docks*, say — is kept as you wrote it. Extraction files near-identical wordings under the list's version (*Structure* becomes *Structural*, *HVAC* becomes *Mechanical*), but components already in your registry keep their existing wording until someone edits them.

### Finding things in a long registry

A registry extracted from a report can run to ninety rows, so it's a table you can narrow:

| Control | Offers |
| --- | --- |
| **Search** | The component's name and category |
| **Category** | The categories in use, plus *No category* |
| **Due** | Already past · within 3, 5 or 10 years · more than 10 years · no remaining life |
| **Figures** | *In the projection* (both cost and remaining life recorded) or *Missing figures* |
| **Sort** | Soonest due, costliest, or name A–Z |

A component with no remaining life is never swept into a dated window — it isn't *far away*, it's unanswered, which is what the *No remaining life* option is for. **Missing figures** is the one to run after an extraction: it lists exactly the rows the projection can't see.

Each row shows the year it's due and how far off that is. **Due soon** marks anything within three years; **Overdue** marks anything whose year has already gone by. On a phone the table becomes one card per component.

### When a component is due

A remaining life is counted from **the year it was written down**, not from today. A component extracted from a 2021 report that gave it 2 years left was due in **2023** — and if you're reading it in 2026, it's shown as **Overdue**, not as due in 2028.

- **Extracted** components count from the study's report date.
- **Added or edited by hand**, a new remaining life counts from today. Changing the name or cost of a component doesn't move its year — only changing the remaining life does.

The page says how old the figures are — *counted from your depreciation report of 2021, so they are 5 years old* — and how many components have passed their year. Overdue components count as **needed now** in the projection, not as negative time.

> **An old report makes the recommendation go up**
>
> Counting from the report's own year means a stale study puts more work inside
> the planning horizon, so the recommended contribution rises. That's the honest
> reading: the work the study expected hasn't gone away because the years passed.
> Review the overdue rows — schedule the work, or correct the figure if it's been
> done.

### Correcting a component

Every row has three icons:

- **Pencil** — edit the component in place. A cost read crookedly out of a study table is a correction, not a delete-and-retype, and editing keeps the component's link to the study it came from (which matters for [s.96(b)](#reserve-work-and-the-majority-vote)).
- **Wrench** — raise a [work order](https://managestrata.ca/docs/property/maintenance) for it. The job is filed on your Maintenance page with the component already attached.
- **×** — remove it, after a preview of what's being removed.

### Keeping it current

- **When work is done,** correct the component's remaining life (and cost, if it changed). A roof replaced this year shouldn't still show as due.
- **Raise the work from the row.** A work order raised with the wrench is linked to its component, which is what connects the plan to what was actually spent.
- **Revisit costs annually.** Construction costs in Canada have moved sharply; a 2019 replacement cost is not a 2026 replacement cost.
- **Add what the report missed.** Studies work to a scope. If you know about something, add it.

### Reserve work and the majority vote

CRF spending normally needs a 3/4 vote; work **recommended in your most current depreciation report** needs only a majority (s.96(b)). When a work order is linked to a component that came from your **current** study, the job page says so beside that choice. A component from a superseded study doesn't count. Whether the report actually recommends *this work* is still the council's call — see [maintenance](https://managestrata.ca/docs/property/maintenance#how-its-paid).

## The reserve projection

Once some components carry both figures, the **Assets & reserve study** page shows a **Contingency Reserve Fund (CRF) projection** above the registry:

*Illustration — ManageStrata · Assets — Contingency Reserve Fund (CRF) projection:*

      <p className="text-[11px] font-bold uppercase tracking-wide text-subtle-foreground">Due in 5y</p>
      <p className="mt-1 text-xl font-extrabold tabular-nums text-foreground">$730,000</p>

      <p className="text-[11px] font-bold uppercase tracking-wide text-subtle-foreground">Balance today</p>
      <p className="mt-1 text-xl font-extrabold tabular-nums text-foreground">$248,000</p>

      <p className="text-[11px] font-bold uppercase tracking-wide text-subtle-foreground">Annual need</p>
      <p className="mt-1 text-xl font-extrabold tabular-nums text-foreground">$96,400</p>

      <p className="text-[11px] font-bold uppercase tracking-wide text-subtle-foreground">Recommended/yr</p>
      <p className="mt-1 text-xl font-extrabold tabular-nums text-foreground">$96,400</p>

It's study-based: the replacement costs coming due within the planning horizon (five years in BC), less the reserve balance today, spread over those years.

**Set the Reserve (CRF) contribution** takes you to the [budget](https://managestrata.ca/docs/finances/budgets#the-reserve-line-and-the-recommendation), where the same recommendation sits beside the reserve line you're setting. Compliance scores the reserve lines in your **adopted budget** against it — not the figure on this page. What to do with a shortfall is covered in [contingency reserve fund](https://managestrata.ca/docs/compliance/reserve-fund) — raise the contribution, re-time the work, raise a levy, or borrow.

> **A projection is a model**
>
> It assumes today's costs, today's estimates, and today's contribution. Real
> buildings surprise people. Use it to see the shape of the problem and to compare
> options — not as a promise about 2041.

## Using it at a meeting

This page is the most persuasive thing a council has when asking owners for money. A [special levy](https://managestrata.ca/docs/finances/special-levies) presented alongside the projection reads as an unavoidable consequence of the numbers. The same levy presented on its own reads as a request, and gets treated like one.

Owners can check whether the depreciation report is current on the read-only compliance page, which opens at its address though it isn't in their menu. Publishing the projection alongside it — in the AGM package or as an [announcement](https://managestrata.ca/docs/people/announcements) — is worth doing.

## If you have no report yet

You can still build a registry by hand. It's better than nothing and much worse than a professional study: it will miss things, and the things it misses are the expensive ones.

If you're in BC with five or more lots, you're required to have a report anyway, on a deadline that depends on your regional district. Start there. See [depreciation report](https://managestrata.ca/docs/compliance/depreciation-report).

## A yearly rhythm

| When | Do |
| --- | --- |
| With the budget | Review the projection; set next year's contribution against it |
| When work completes | Correct the component's remaining life; make sure the work order is linked to it |
| Annually | Refresh replacement costs |
| Every 3–5 years | New study, per your province; record it from Compliance and re-seed |